1 |
Construction pf 10km Okitipupa-Igbokoda Bye-Pass Road Phase 1 |
Okitipupa-Igbokoda |
6,116,919,483.80 |
05/03/2021 |
36 months |
Craneburg Nig, Ltd., No. 12 Adekunle Ajasin road, Nepa, Akure, Ondo State |
Construction pf 10km Okitipupa-Igbokoda Bye-Pass Road Phase 1 |
Ministry of Works/Engr Allen Idowu/08033500910 |
2 |
Construction/Rehabilitation of 10.0km |
Oba-Ikun-Afo Road, Phase 1 |
2,679,314.79 |
30/11/2020 |
36 months |
Arc Marine & Civil Contractor Ltd, No. 1, Arc Road, off ELF Road, Idugboe Estate, Ogunnu, D |
Construction/Rehabilitation of 10.0km |
Ministry of Works/Engr Allen Idowu/08033500910 |
3 |
Construction of 4.7km dual carriage road |
Ikare Junction - FMC - Mobil Junction - Ifesanmi Junction Road, Owo, Ondo State. |
8,885,362,885.53 |
16/11/2020 |
36 month |
Craneburg Nig, Ltd., No. 12 Adekunle Ajasin road, Nepa, Akure, Ondo State |
Construction of 4.7km dual carriage road |
Ministry of Works/Engr Allen Idowu/08033500910 |
4 |
Construction of 814m (New Jersey) concrete barrier to be placed at the median of Oba Adesida Road from Araromi junction to Esso, Akure, Ondo State. |
Oba Adesida Road from Araromi junction to Esso, Akure, Ondo State. |
151,640,093.53 |
16/11/2020 |
6 months |
Craneburg Nig, Ltd., No. 12 Adekunle Ajasin road, Nepa, Akure, Ondo State |
Construction of 814m (New Jersey) concrete barrier to be placed at the median of Oba Adesida Road from Araromi junction to Esso, Akure, Ondo State. |
Ministry of Works/Engr Allen Idowu/08033500910 |
5 |
Construction/Rehabilitation of 6.6km Oke Odu-Ijare Road with spurs to Ipinsa, Ikota and AAVE and Selected road in Ijare and Ero town |
Oke Odu-Ijare Road with spurs to Ipinsa, Ikota and AAVE and Selected road in Ijare and Ero town |
2,107,276,920.30 |
27/10/2020 |
24 months |
Elementary Engineering Consult Ltd., Dr. Soji Omowole, Airport road, Oba Ile, Akure, Ondo State. |
Construction/Rehabilitation of 6.6km Oke Odu-Ijare Road with spurs to Ipinsa, Ikota and AAVE and Selected road in Ijare and Ero town |
Ministry of Works/Engr Allen Idowu/08033500910 |
6 |
Production of 2020 Christmas Cards |
Akure |
1,846,590.91 |
27/10/2020 |
1 Year |
Publicist Intergrated Sevice Ltd, 25 Ikere St, Ijapo, Akure |
Production of 2019 Christmas Cards |
Ministry of Information/08037779402 |
7 |
Production of 2021 Calendars |
Akure |
18,750,000.00 |
27/10/2020 |
1 Year |
Publicist Intergrated Sevice Ltd, 25 Ikere St, Ijapo, Akure |
Production of 2019 Christmas Cards |
Ministry of Information/08037779402 |
8 |
Production of 2021 Desk Diaries |
Akure |
40,909,090.91 |
27/10/2020 |
1 Year |
Doable African Global Concept, 1 Oduntola St, Oke Ado, Ibadan |
Production of 2021 Desk Diaries |
Ministry of Information/08037779402 |
9 |
Matching Investment on the Quick Win Project in the State Urban Water Sector |
Oke Igbo, Oke Igbo/Ile Oluji LGA |
72,797,515.83 |
10/10/2020 |
3 Months |
Times & Associate Construction Ltd, 20 Road 4, Ave 1, Ilupeju Ave, Ondo-Ife Road, Ondo |
Rehabilitation of Oke Igbo Water Supply Scheme |
Ondo State Water Corp./Engr Akinrinmade/08037246209 |
10 |
Matching Investment on the Quick Win Project in the State Urban Water Sector |
Oba Akoko, Akoko South West LGA |
79,009,729.15 |
10/10/2020 |
3 Months |
Hillstar Nigerian Ltd, 1, Ondo Close, Bodija, Ibadan, |
Rehabilitation of Ako Spring Water Supply Scheme |
Ondo State Water Corp./Engr Akinrinmade/08037246209 |
11 |
Matching Investment on the Quick Win Project in the State Urban Water Sector |
Ilutitun, Okitipupa LGA |
69,198,989.36 |
10/10/2020 |
3 Months |
Taibun Engineering Works Ltd, Abeleje Shopping Complex, Behind NNPC Petrol Station, Shagari Akure |
Rehabilitation of Ilutitun Water Supply Scheme |
Ondo State Water Corp./Engr Akinrinmade/08037246209 |
12 |
Matching Investment on the Quick Win Project in the State Urban Water Sector |
Okitipupa, Okitipupa LGA |
16,425,730.41 |
10/10/2020 |
1 Month |
Taibun Engineering Works Ltd, Abeleje Shopping Complex, Behind NNPC Petrol Station, Shagari Akure |
Rehabilitation of Okitipupa Water Supply Scheme |
Ondo State Water Corp./Engr Akinrinmade/08037246209 |
13 |
Matching Investment on the Quick Win Project in the State Urban Water Sector |
Idoani, Ose LGA |
61,449,867.60 |
10/10/2020 |
3 Months |
Lerick Nigeria Ltd, Suite 49, Akure Shopping Complex, Alagbaka, Akure, Ondo State |
Rehabilitation of Okitipupa Water Supply Scheme |
Ondo State Water Corp./Engr Akinrinmade/08037246209 |
14 |
Construction/Rehabilitation of 9.75km UTE Township |
UTE Township |
1,226,383,342.97 |
14/09/2020 |
18 months |
Rembam Nig. Ltd., Blocks 24A, Plot 2, Festac Link Road, Amuwo Odofin, Lagos State |
Construction/Rehabilitation of 9.75km UTE Township |
Ministry of Works/Engr Allen Idowu/08033500910 |
15 |
Rehabilitation of criticallly failed portion at Ita Ipele along Owo/Benin Express way and construction/rehabilitation of 4.515km Araromi, Ifon and Ikaro township roads |
Ita Ipele along Owo/Benin Express way and Araromi, Ifon and Ikaro township roads |
1,504,851,005.31 |
14/09/2020 |
12 months |
RCF Nig. Limited, No. 14, Fagba Cresent Road, Lagos State |
Rehabilitation of criticallly failed portion at Ita Ipele along Owo/Benin Express way and construction/rehabilitation of 4.515km Araromi, Ifon and Ikaro township roads |
Ministry of Works/Engr Allen Idowu/08033500910 |
16 |
Construction/Rehabilitation of 4.219km |
Owo Phase A |
1,464,227,757.26 |
14/05/2020 |
24 months |
Oceanic Construction Engineering Nig. Ltd., 4C, Olatunbosun Street. Shonibare Estate, Maryland, Lagos State. |
Construction/Rehabilitation of 4.219km Owo (Phase A) |
Ministry of Works/Engr Allen Idowu/08033500910 |
17 |
Construction/Rehabilitation of 16.625km Akunnu - Ikaramu - OkeAgbe |
Akunnu - Ikaramu - OkeAgbe Akoko |
4,327,122.40 |
27/03/2020 |
36 months |
Carreggiata Nig. Ltd, Plt G IV, Olugboja Street, Alagbaka Quarters, Akure, Ondo State. |
Construction/Rehabilitation of 16.625km Akunnu - Ikaramu - OkeAgbe |
Ministry of Works/Engr Allen Idowu/08033500910 |
18 |
Dualization of Akure-Oda Road (Phase 1) up to CH 4 + 000 Including Rehabilitation from CH 4 + 000-CH 7 + 805 |
Akure-Oda Road |
4,488,935,271.49 |
27/03/2020 |
18 months |
Dortmund and Company Ltd, Plts 4 & 5, State Industrial Layout, Akure, Ondo State |
Dualization of Akure-Oda Road (Phase 1) up to CH 4 + 000 Including Rehabilitation from CH 4 + 000-CH 7 + 805 |
Ministry of Works/Engr Allen Idowu/08033500910 |
19 |
Construction/Rehabilitation of 5.422km Araromi-Obu Township Road |
Araromi-Obu |
1,368,006,931.11 |
25/03/2020 |
12 months |
Immobiliare Construction Ltd., No. 27a, Furo Ezimora Street, Lekki Phase 1, Lagos State |
Construction/Rehabilitation of 5.422km Araromi-Obu Township Road |
Ministry of Works/Engr Allen Idowu/08033500910 |